Rs 450 million due to a geological problem which had not been previously detected. And this is to prevent leaks due to this state of things the Chinese company, China International Water and Electric (CIWE) requires this additional amount. And the project cost increased from Rs 3.3 billion to Rs 3.7 billion.
To prevent the dam turns into a colander, a reinforced concrete structure will be built in the basement.